There are instances that production machines require a warm-up period to reach their anticipated productivity. This study extends an economic manufacturing quantity (EMQ) problem by considering warm-up issue in the model. Warming up the machine decreases production loss, emission, and machine depreciation. Therefore, this study helps industry to enhance the profitability and also to reduce the environmental impact by decreasing waste generation and improving machine efficiency. In this study, we divide our system into three subsystems based on the relationships between production and consumption. Then we provide a mathematical model for each subsystem (three in total). The first two models are single-item EMQ inventory problems and the third one is a multi-item single-machine EMQ problem. In the third model, a machine/facility manufactures some items under a limited manufacturing volume. The purpose of these proposed models is to find the optimum cycle length to minimize the total system cost that consists of manufacturing, inventory and setup costs. Finally, we propose exact solution procedures after proving the convexity of these mathematical models.
Accepté le :
Première publication :
Publié le :
DOI : 10.1051/ro/2019056
Mots-clés : Economic manufacturing quantity (EMQ), single machine production, warm-up period, non-linear programming (NLP), exact solution
@article{RO_2020__54_5_1495_0, author = {Nobil, Amir Hossein and Kazemi, Abolfazl and Taleizadeh, Ata Allah}, title = {Economic lot-size problem for a cleaner manufacturing system with warm-up period}, journal = {RAIRO - Operations Research - Recherche Op\'erationnelle}, pages = {1495--1514}, publisher = {EDP-Sciences}, volume = {54}, number = {5}, year = {2020}, doi = {10.1051/ro/2019056}, mrnumber = {4126317}, language = {en}, url = {http://www.numdam.org/articles/10.1051/ro/2019056/} }
TY - JOUR AU - Nobil, Amir Hossein AU - Kazemi, Abolfazl AU - Taleizadeh, Ata Allah TI - Economic lot-size problem for a cleaner manufacturing system with warm-up period JO - RAIRO - Operations Research - Recherche Opérationnelle PY - 2020 SP - 1495 EP - 1514 VL - 54 IS - 5 PB - EDP-Sciences UR - http://www.numdam.org/articles/10.1051/ro/2019056/ DO - 10.1051/ro/2019056 LA - en ID - RO_2020__54_5_1495_0 ER -
%0 Journal Article %A Nobil, Amir Hossein %A Kazemi, Abolfazl %A Taleizadeh, Ata Allah %T Economic lot-size problem for a cleaner manufacturing system with warm-up period %J RAIRO - Operations Research - Recherche Opérationnelle %D 2020 %P 1495-1514 %V 54 %N 5 %I EDP-Sciences %U http://www.numdam.org/articles/10.1051/ro/2019056/ %R 10.1051/ro/2019056 %G en %F RO_2020__54_5_1495_0
Nobil, Amir Hossein; Kazemi, Abolfazl; Taleizadeh, Ata Allah. Economic lot-size problem for a cleaner manufacturing system with warm-up period. RAIRO - Operations Research - Recherche Opérationnelle, Tome 54 (2020) no. 5, pp. 1495-1514. doi : 10.1051/ro/2019056. http://www.numdam.org/articles/10.1051/ro/2019056/
[1] Economic lot scheduling problem with imperfect production processes. J. Oper. Res. Soc. 51 (2000) 875–881. | DOI | Zbl
and ,[2] Determining the optimal lot size for the finite production model with random defective rate, the rework process, and backlogging. Eng. Optimiz. 35 (2003) 427–437. | DOI
,[3] Determining the optimal run time for EPQ model with scrap, rework, and stochastic breakdowns. Eur. J. Oper. Res. 180 (2007) 664–676. | DOI | Zbl
, and ,[4] Quality and pricing decisions for substitutable items under imperfect production process over a random planning horizon. Hacet. J. Math. Stat. 47 (2018) 175–201. | MR
, and ,[5] Scheduling for batch production. J. Inst. Prod. Eng. 36 (1957) 549–570. | DOI
,[6] The economic lot scheduling problem (ELSP): review and extensions. Manage. Sci. 24 (1978) 587–598. | DOI | Zbl
,[7] Scheduling economic lot sizes in deteriorating production systems. Nav. Res. Log. 50 (2003) 650–661. | DOI | MR | Zbl
, and ,[8] Optimal batch production for a single machine system with accumulated defectives and random rate of rework. J. Ind. Syst. Eng. 3 (2010) 243–256.
and ,[9] Lot sizing with non-zero setup times for rework. J. Syst. Sci. Syst. Eng. 17 (2008) 230–240. | DOI
, , and ,[10] Lot sizing in a production system with rework and product deterioration. Int. J. Prod. Res. 43 (2005) 1355–1374. | DOI | Zbl
, and ,[11] Optimal production lot sizing with backlogging, random defective rate, and rework derived without derivatives. Proc. Inst. Mech. Eng. Part B: J. Eng. Manuf. 223 (2009) 1081–1084. | DOI
,[12] Two layers green supply chain imperfect production inventory model under bi-level credit period. Tékhne 15 (2017) 124–142. | DOI
, , and ,[13] Imperfect production inventory model with production rate dependent defective rate and advertisement dependent demand. Comput. Ind. Eng. 104 (2017) 9–22. | DOI
, and ,[14] Two layers supply chain in an imperfect production inventory model with two storage facilities under reliability consideration. J. Ind. Prod. Eng. 35 (2018) 57–73.
, and ,[15] Impact of carbon emission on imperfect production inventory system with advance payment base free transportation. RAIRO-Oper. Res. (2019). DOI: . | DOI | Numdam | MR
, and ,[16] Economic lot scheduling problem with imperfect production processes and setup times. J. Oper. Res. Soc. 53 (2002) 620–629. | DOI | Zbl
, and ,[17] Some observations to: lot sizing with non-zero setup times for rework. Int. J. Appl. Comput. Math. 3 (2017) 1511–1517. | DOI | MR
, and ,[18] A multiproduct single machine economic production quantity (EPQ) inventory model with discrete delivery order, joint production policy and budget constraints. Ann. Oper. Res. (2017) 1–37. | MR | Zbl
, and ,[19] An imperfect multi-item single machine production system with shortage, rework, and scrapped considering inspection, dissimilar deficiency levels, and non-zero setup times. Sci. Iran. 26 (2019) 557–570.
, , and ,[20] Economic production quantity model considering warm-up period in a cleaner production environment. Int. J. Prod. Res. 57 (2019) 4547–4560. | DOI
, and ,[21] Optimal cycle length and number of inspections in imperfect production processes with investment on setup cost reduction and quality improvement. Int. J. Manuf. Res. 4 (2009) 17–36. | DOI
and ,[22] A multiproduct single machine economic production quantity model for an imperfect production system under warehouse construction cost. Int. J. Prod. Econ. 169 (2015) 203–214. | DOI
, , and ,[23] Sequencing, lot sizing and scheduling of several products in job shops: the common cycle approach. Int. J. Prod. Res. 36 (1998) 1125–1140. | DOI | Zbl
and ,[24] A computational approach to the economic lot scheduling problem. Manage. Sci. 4 (1958) 264–291. | DOI
,[25] Pricing and production decisions in multi-product single machine manufacturing system with discrete delivery and rework. Opsearch 53 (2016) 873–888. | DOI | MR
, and ,[26] The most economical production lot. Iron Age 101 (1918) 1410–1412.
,[27] Manufacturing system with immediate rework and partial backordering. Int. J. Adv. Oper. Manage. 7 (2015) 41–62.
and ,Cité par Sources :