In this paper we develop new elimination rules and discuss several polynomially solvable cases for the two-stage hybrid flow shop problem with dedicated machines. We also propose a worst case analysis for several heuristics. Furthermore, we point out and correct several errors in the paper of Yang [J. Yang, A two-stage hybrid flow shop with dedicated machines at the first stage. Comput. Oper. Res. 40 (2013) 2836−2843].
Accepté le :
DOI : 10.1051/ro/2015005
Mots-clés : Scheduling, hybrid flow shop, dedicated machines, worst case analysis, elimination rule
@article{RO_2015__49_4_795_0, author = {Hadda, Hatem and Hajji, Mohamed Karim and Dridi, Najoua}, title = {On the two-stage hybrid flow shop with dedicated machines}, journal = {RAIRO - Operations Research - Recherche Op\'erationnelle}, pages = {795--804}, publisher = {EDP-Sciences}, volume = {49}, number = {4}, year = {2015}, doi = {10.1051/ro/2015005}, zbl = {1323.90021}, language = {en}, url = {http://www.numdam.org/articles/10.1051/ro/2015005/} }
TY - JOUR AU - Hadda, Hatem AU - Hajji, Mohamed Karim AU - Dridi, Najoua TI - On the two-stage hybrid flow shop with dedicated machines JO - RAIRO - Operations Research - Recherche Opérationnelle PY - 2015 SP - 795 EP - 804 VL - 49 IS - 4 PB - EDP-Sciences UR - http://www.numdam.org/articles/10.1051/ro/2015005/ DO - 10.1051/ro/2015005 LA - en ID - RO_2015__49_4_795_0 ER -
%0 Journal Article %A Hadda, Hatem %A Hajji, Mohamed Karim %A Dridi, Najoua %T On the two-stage hybrid flow shop with dedicated machines %J RAIRO - Operations Research - Recherche Opérationnelle %D 2015 %P 795-804 %V 49 %N 4 %I EDP-Sciences %U http://www.numdam.org/articles/10.1051/ro/2015005/ %R 10.1051/ro/2015005 %G en %F RO_2015__49_4_795_0
Hadda, Hatem; Hajji, Mohamed Karim; Dridi, Najoua. On the two-stage hybrid flow shop with dedicated machines. RAIRO - Operations Research - Recherche Opérationnelle, Tome 49 (2015) no. 4, pp. 795-804. doi : 10.1051/ro/2015005. http://www.numdam.org/articles/10.1051/ro/2015005/
Méthode heuristique pour le problème de flow shop hybride avec machines dédiées. RAIRO – Oper. Res. 43 (2009) 421–36. | DOI | Numdam | Zbl
, and ,A note on “A heuristic method for two-stage hybrid flow shop with dedicated machines”. Comput. Oper. Res. 40 (2013) 2283. | DOI | Zbl
,H. Hadda, N. Dridi and S. Hajri-Gabouj, Etude du flow shop hybride à deux étages avec machines dédiées sous contrainte d'indisponibilité. In Proc. 5th International Conference. Rabat, Morocco (2007).
A note on the two-stage hybrid flow shop problem with dedicated machines. Optim. Lett. 6 (2012) 1731–1736. | DOI | Zbl
, and ,The two-stage assembly flow shop scheduling with an availability constraint: worst case analysis. J. Math. Modell. Algorithms Oper. Res. 13 (2014) 233–245. | Zbl
, and ,Exact resolution of the two-stage hybrid flow shop with dedicated machines. Optim. Lett. 8 (2014) 2329-2339. | DOI | Zbl
, and ,Optimal two- and three-stage production schedules with setup times included. Naval Res. Logist. Quart. 1 (1954) 61–68. | DOI | Zbl
,The strong NP-hardness of two-stage flowshop scheduling with a common second-stage machine. Comput. Oper. Res. 26 (1999) 695–698. | DOI | Zbl
,Two-stage flowshop with a common second-stage machine. Comput. Oper. Res. 24 (1997) 1169–1174. | DOI | Zbl
, and ,The two-stage assembly scheduling problem: Complexity and approximation. Oper. Res. 43 (1995) 346–355. | DOI | Zbl
, , , and ,A heuristic for two-stage hybrid flow shop with dedicated machines. Comput. Oper. Res. 40 (2013) 438–450. | DOI | Zbl
and ,A two-stage hybrid flow shop with dedicated machines at the first stage. Comput. Oper. Res. 40 (2013) 2836–2843. | DOI | Zbl
,Cité par Sources :